Library

Video Player is loading.
 
Current Time 14:45
Duration 5:20
Loaded: 0.00%
 
x1.00


Back

Games & Quizzes

Training Mode - Typing
Fill the gaps to the Lyric - Best method
Training Mode - Picking
Pick the correct word to fill in the gap
Fill In The Blank
Find the missing words in a sentence Requires 5 vocabulary annotations
Vocabulary Match
Match the words to the definitions Requires 10 vocabulary annotations

You may need to watch a part of the video to unlock quizzes

Don't forget to Sign In to save your points

Challenge Accomplished

PERFECT HITS +NaN
HITS +NaN
LONGEST STREAK +NaN
TOTAL +
- //

We couldn't find definitions for the word you were looking for.
Or maybe the current language is not supported

  • 00:00

    hello everyone welcome to my channel PMP with Ray. I am Ray, and I'm a PMP

  • 00:06

    certified project manager in this channel I am here to help you pass your

  • 00:11

    PMP exam in the first attempt

  • 00:18

    now when I took my PMP exam seven to eight months back there was one area

  • 00:24

    which I really struggled with and that was integrated change control system (PICC) if

  • 00:29

    you are also struggling to solve questions from the integrated change

  • 00:32

    control process you will find this video very helpful when I was reading this

  • 00:37

    subject and trying to answer questions I was getting a lot of questions wrong but

  • 00:41

    the issue was I was not able to understand why I was getting those

  • 00:45

    particular questions wrong now when I try to analyze that why I was getting

  • 00:50

    the questions from integrated change control wrong, I found out that to answer

  • 00:54

    those questions in a correct manner there is a sequence of steps which is

  • 00:59

    required to be remembered or which is required to be memorized to answer those

  • 01:05

    questions correctly and the funny part is if you miss any particular part of

  • 01:10

    that sequence, you will get those questions wrong so let's go back to the

  • 01:14

    whiteboard take a look at the flow chart and solve some questions

  • 01:19

    [Music] welcome to the whiteboard we will

  • 01:27

    understand the integrated change control flowchart through a scenario which is

  • 01:31

    displayed on the screen it goes as you are the project manager

  • 01:35

    and your project is to purchase and deliver an iPhone 10 to your friend who

  • 01:39

    is Angela so here your client is Angela and for this example let us take that

  • 01:45

    your sponsor is XYZ bank or who is financing the phone for Angela so as we

  • 01:51

    develop the CMP flowchart now we will keep this example as our reference so

  • 01:56

    the first step of change control process our request comes for a change so if you

  • 02:11

    take this example maybe Angela comes to you and says that she wants an iPhone 11

  • 02:18

    or but not our iPhone 10 so that is a change so what request comes for a

  • 02:23

    change that is step one next what do you have to do is you have to ask what the

  • 02:37

    change is to your customer so that is mostly top-line because often maybe

  • 02:48

    Angela can come to you one day and ask that hey I want a change to my iPhone so

  • 02:53

    that doesn't mean anything so you need to ask her that okay what is the change

  • 02:57

    you are asking so then he/she says that okay I want i phone 11 but not an iPhone

  • 03:02

    10 so that's what is this step about next is document and

  • 03:15

    create a formal change request now this is the most important step guys and this

  • 03:35

    gets skipped very often so what are your Knicks need to do is after you know that

  • 03:41

    angela is asking for a iPhone 11 and order iPhone 10 you need to first

  • 03:46

    document this change on a proper change request

  • 03:49

    next is link the change to project scope

  • 04:10

    now here what you will do is you will go to the project charter and check that

  • 04:14

    okay what was the project about so for this example let us take that the

  • 04:18

    project was to buy her iPhone for Angela so that's okay now maybe he wants a

  • 04:24

    higher version so that is a change but no doubt it is linked to the project

  • 04:28

    scope because maybe the project scope is just to buy her an iPhone so that's with

  • 04:35

    this particular step now here after this step comes a

  • 04:38

    decision point okay a decision point what is meant is there NBI yes or there

  • 04:45

    can be a no now the first scenario that this change is not linked to the project

  • 04:54

    scope then what you need to do consider

  • 05:02

    as separate scope or project now this is very important that you need to go back

  • 05:20

    to the customer and say that hey this change is not linked to the project

  • 05:24

    charter so it's better that we consider it as a separate project and not take it

  • 05:28

    as a part of this project so you can go and tell Angela that okay maybe the

  • 05:33

    higher version is not within the scope so it you have to consider it as a

  • 05:37

    separate project now if this is yes that you agree that it is a part of the

  • 05:45

    project scope then the next step is

  • 05:50

    within teams evaluate the impact of the change

  • 06:15

    now what this means is that you need to go back to the drawing board and see

  • 06:21

    that whether this change is affecting the schedule affecting the cost

  • 06:24

    affecting the resources affecting the communications affecting the quality

  • 06:28

    affecting the procurement so you need to go through each of the ten knowledge

  • 06:32

    areas of PMBOK and understand that what this particular change impacts in terms

  • 06:38

    of the knowledge areas and it is very important to go through this in detail

  • 06:43

    because that is what will take you through the to the next step which is so

  • 06:53

    this next step is more there are two parts to it one is internal which is go

  • 07:03

    to your sponsor and discuss change implications

  • 07:22

    and the external part goes as go to your customer and same now let us take this

  • 07:44

    example that iPhone 11 maybe costs $1,500 more than iPhone 10 so in this

  • 07:51

    internal aspect what you need to do is you go back to your sponsor which is

  • 07:57

    your XYZ bank right here and tell them that there will be an extra cost of

  • 08:03

    $1,500 in the project are they okay to it or is your sponsor okay to it that is

  • 08:08

    the first step second step you go to Angela who is your customer and ask that

  • 08:14

    okay since she is going for an iPhone 11

  • 08:18

    which is of a higher version than iPhone 10 there will be an incremental cost of

  • 08:22

    $1,500 is she okay with it now this step is called the icc loop so what

  • 08:34

    essentially happens in this step is within the sponsor and the client both

  • 08:40

    of them gets aligned with the impact of the change now the impact may be in

  • 08:44

    terms of cost only which is may be this particular iPhone it costs there is an

  • 08:48

    impact only in terms of cost may be the impact can be in terms of schedule so

  • 08:52

    maybe iPhone 11 will take 15 days more to procure than iPhone 10

  • 08:57

    so both the sponsor and Angela both of them should be aware and should align

  • 09:02

    that okay it is acceptable to have 15 days more of a schedule hurt and a cost

  • 09:09

    hurt of $1,500 to get thus this scope or get this change aligned now when this

  • 09:16

    change is aligned with in the ICC loop that both the sponsor and the customer

  • 09:21

    both are aware of what the impact of change is in terms of the 10 knowledge

  • 09:26

    area then comes the next step which is the change is taken to the

  • 09:31

    take change request to change control board now this may be something new for

  • 09:44

    some of the organizations because other than the core project management

  • 09:48

    organizations there doesn't exist a change control board but the ideal role

  • 09:54

    of this board is to evaluate all the changes coming from the different

  • 09:57

    projects so this is an independent body which is present in a company which

  • 10:01

    evaluates all the chains coming from the different projects running at the same

  • 10:04

    time in the company now after this ICC loop is closed then the change is taken

  • 10:09

    to the change control board okay with both the positives and negatives of the

  • 10:18

    change now a change can also be positive guys like if this we take this example

  • 10:28

    maybe iPhone 11 costs $1,500 more but maybe it is quicker to procure than

  • 10:33

    iPhone 10 okay so there can be a positive change that by going to I phone

  • 10:38

    11 we can expedite the schedule by 7 days so you can also think like this now

  • 10:44

    the next step which is after this change is taken to the change control boards

  • 10:50

    there is another decision point and this decision points has three arcs to it

  • 11:02

    maybe three options first is approval that the change is approved by the

  • 11:12

    change control board so the change Control Board says okay go ahead and

  • 11:16

    proc your iPhone 11 and we are okay to take the heart of $1500 and 14 days to

  • 11:21

    get a iPhone 11 rather than iPhone 10 the second option may be a change goes

  • 11:28

    on hold that the change control board is not very sure or maybe they can say that

  • 11:36

    this step is not done properly now maybe there has been some confusions in terms

  • 11:42

    of some of the knowledge so the change control can board can tell

  • 11:46

    the project manager to go back and revisit the impact and come back to them

  • 11:50

    the third one will be rejected so the change Control Board says that Angela

  • 12:00

    should remain happy with iPhone 10 and she will not get iPhone 11 so that's

  • 12:05

    okay yeah now what happens when the change is

  • 12:09

    approved you update change log and

  • 12:27

    execute so once the change is approved you get all the funds you have all the

  • 12:33

    alignments in place you update the change log and go ahead and execute the

  • 12:39

    change if it is on hold then what do you do you update the change log as well

  • 12:53

    here and put it on hold so change log the repository of all the changes which

  • 13:02

    has come or which is coming or which will be coming for us for a project and

  • 13:06

    it has a categorization of which changes are approved which are on hold or which

  • 13:11

    are rejected so a change on hold means maybe the change Control Board will

  • 13:15

    visit this change once again in a couple of days now if it is rejected will you

  • 13:21

    close the loop here maybe not so the important thing here also is you need to

  • 13:27

    update the change log

  • 13:38

    this step as we talked right now which is updating the changelog is a very

  • 13:43

    important one and it often gets missed by a lot of MP candidates okay and they

  • 13:50

    say that okay if the change is rejected we go ahead and close the project or

  • 13:54

    move ahead with the project and they miss out on this option it is very

  • 13:58

    important please keep in mind that without updating the change lock no

  • 14:01

    change loop is closed another important point which I will write just here is

  • 14:08

    sponsor is the final approver okay of any change now this is very important

  • 14:28

    guys I have personally got two to three questions wrong in some of my mock exams

  • 14:34

    where it may blindfold you or it may confuse you by saying that okay the CCP

  • 14:40

    approves the change or the CCP puts the change on hold it's it's not like that

  • 14:45

    as per PMBOK the sponsor is the final approver of change now even if CCP goes

  • 14:52

    ahead and gives them recommendation that the change is rejected if the sponsor

  • 14:57

    thinks that the change needs to be done it will be done so it is very important

  • 15:02

    to keep in mind that the sponsor is the final approver

  • 15:06

    with that we come to the closure of the

  • 15:12

    CMP flowchart okay now what you need to do is you need to go through this chart

  • 15:18

    again step by step and understand that which step is with what intent that is

  • 15:25

    very important and try to answer some questions so with respect to this

  • 15:31

    particular flowchart and that will really help so next what we will do is

  • 15:34

    we will take up two quick questions from Rita Mulkey and use this flow chart

  • 15:39

    which you write see on your screen to solve those questions and you will see

  • 15:43

    the beauty of this flow chart that how this flow chart with easily help you

  • 15:47

    will easily help you to eliminate the wrong options and choose the right

  • 15:51

    options so we move on to question number one

  • 15:54

    this is the first question feel free to pause the video and take a shot at it

  • 16:02

    now the answer to this question lies here which is the change control flow

  • 16:11

    chart now what this question is asking it is asking that the primary customer

  • 16:16

    of a project has requested an application change and now how should

  • 16:21

    you address the issue the correct answer to this question is option B which is

  • 16:29

    create a formal change request now why is this option correct if you see here

  • 16:37

    the customer has requested and change application change okay now if you go to

  • 16:43

    this portion of the flowchart what it says that after a request comes and you

  • 16:51

    know that what the customer is asking that you know that up line what the

  • 16:55

    change is document and create a formal change request and that's why option B

  • 17:01

    is the correct option now if you go with develop a risk management plan or inform

  • 17:07

    the project sponsor of the changes to cost hope excetra which essentially

  • 17:12

    links to these steps of icc loop you will get the question wrong because it

  • 17:19

    violates the flow chart or the flow of the change management process so the

  • 17:24

    correct answer to this question is option B this one is the second

  • 17:31

    question-it is also from rita Mulkey pause the video and try to answer this

  • 17:36

    question the correct answer to this question is option number D which is

  • 17:41

    evaluate the impact on other project constraints now why is this option

  • 17:46

    correct if you focus on this part of the CNP flowchart it says that after a

  • 17:52

    formal change request has been created and you have established the linkage to

  • 17:57

    the project scope none of these are present in the options you move on to

  • 18:02

    the evaluation purpose so that is why this option is the most correct option

  • 18:09

    now if there was one option which talked about document the formal change request

  • 18:13

    or try to link the change to project scope that would have been the right

  • 18:18

    answer but if you see these options it does not mention these two steps okay

  • 18:25

    and that is why option D is the correct option option C is wrong and why is that

  • 18:32

    because it talks about a process which happens far down the change control

  • 18:37

    process change control flowchart which is this one so CCP comes into picture

  • 18:43

    here which is later then after you evaluate the changes and with the impact

  • 18:50

    on all okay so that is why option C is wrong and D is the correct answer to

  • 18:55

    this question

  • 18:58

    let me know in the comment section below how you felt about today's video if you

  • 19:03

    have liked the video give me a thumbs up don't forget to subscribe to this

  • 19:07

    channel PM p with ray and press the bell icon to never miss another update i'll

  • 19:11

    see you again in my next video

  • 19:15

    [Music]

All

The example sentences of APPROVER in videos (2 in total of 3)

as preposition or subordinating conjunction per preposition or subordinating conjunction pmbok proper noun, singular the determiner sponsor noun, singular or mass is verb, 3rd person singular present the determiner final adjective approver noun, singular or mass of preposition or subordinating conjunction change noun, singular or mass now adverb even adverb if preposition or subordinating conjunction ccp proper noun, singular goes verb, 3rd person singular present
record noun, singular or mass the determiner comments noun, plural that wh-determiner were verb, past tense left verb, past participle by preposition or subordinating conjunction the determiner approver noun, singular or mass if preposition or subordinating conjunction we personal pronoun close verb, non-3rd person singular present this determiner flow noun, singular or mass and coordinating conjunction

Use "approver" in a sentence | "approver" example sentences

How to use "approver" in a sentence?

  • We thirst for approbation, yet cannot forgive the approver.
    -Ralph Waldo Emerson-

Definition and meaning of APPROVER

What does "approver mean?"

/əˈpro͞ovər/

noun
Authority with power to approve.